Production

Load-In / Load-Out

Load-in and load-out refer to the setup and teardown phases of event production when equipment arrives at a venue and is installed (load-in), then disassembled and removed (load-out). These phases directly impact labor costs and venue rental time requirements.

Understanding Load-In / Load-Out

Load-in and load-out are critical production phases that significantly impact event budgets and timelines. Efficient execution requires careful planning, appropriate crew sizing, and understanding of equipment requirements.

Load-In Phases

**Advance Work:**

  • Review venue access (dock height, door widths, elevator capacity)
  • Confirm power locations and requirements
  • Establish rigging points if flying
  • Create equipment staging plan

**Arrival and Staging:**

  • Truck positioning and unloading
  • Equipment organized in staging area
  • Inventory verification against manifest
  • Damaged equipment identified immediately

**Installation:**

  • Structure assembly (truss, ground support)
  • Panel installation in correct order
  • Cable routing and connection
  • Initial power-up and testing

**Technical Prep:**

  • Signal verification from all sources
  • Brightness and color calibration
  • Content testing
  • Client walk-through and approval

Time Estimation Guidelines

**LED Wall Assembly Rates (experienced crew):**

  • Ground support structure: 30-60 minutes
  • Panel installation: 15-20 panels per hour
  • Cabling and connection: 30-45 minutes
  • Testing and calibration: 30-60 minutes

**Example: 16x9 foot wall (2.9mm pitch)**

  • Approximately 48 panels
  • Structure: 45 minutes
  • Panels: 2.5 hours
  • Cabling: 30 minutes
  • Testing: 45 minutes
  • **Total: 4-5 hours**

Crew Sizing

**Minimum Crew Guidelines:**

  • Small wall (under 100 sq ft): 2-3 technicians
  • Medium wall (100-300 sq ft): 4-6 technicians
  • Large wall (300+ sq ft): 6-10 technicians
  • Complex configurations: Add personnel as needed

Load-Out Considerations

**Speed Factors:**

  • No testing phase required
  • Crew familiar with equipment from load-in
  • Organized packing maintains efficiency
  • Venue pressure may require faster teardown

**Common Challenges:**

  • Overtime charges if exceeding venue time
  • Crew fatigue from long event days
  • Equipment inventory before departure
  • Weather considerations for outdoor events

Venue Access Planning

Critical measurements to confirm:

  • Loading dock height and ramp availability
  • Door dimensions (including height)
  • Elevator capacity and dimensions
  • Distance from dock to installation location
  • Floor protection requirements

Cost Implications

Load-in/load-out typically represents 30-40% of total labor costs for LED wall rentals. Efficient execution saves:

  • Labor hours
  • Venue rental time
  • Equipment rental days
  • Travel and accommodation

Frequently Asked Questions

How long does LED wall load-in typically take?

A standard 16x9-foot LED wall (ground-supported) can be assembled by a 4-person crew in 2-3 hours including cabling and testing. Flown configurations add 1-2 hours for rigging. Larger walls (40x20+ feet) may require 6-8 hours with appropriate crew size.

What equipment is needed for LED wall load-in?

Essential equipment includes: flight cases on wheels, appropriate tools (often minimal with quick-lock panels), cable management supplies, leveling tools for ground support, and test equipment (laptop, signal generator). Flown installations also require rigging hardware and motors.

How do I estimate load-out time?

Load-out is typically faster than load-in (about 60-75% of the time) because there is no testing, calibration, or troubleshooting. However, some venues require faster load-out to avoid overtime charges. Plan crew size accordingly.