Operations Guide

The Complete Guide to LED Video Wall Production Planning

From site survey to show wrap, master the logistics of LED video wall productions. Crew sizing formulas, load-in timelines, cable management, testing protocols, and everything you need to execute productions of any scale.

26 min read|6,500+ words|Intermediate|Updated January 2025

The difference between a production that runs smoothly and one that turns into a fire drill often comes down to planning. LED video walls involve significant logistics: trucking, rigging, power, crew coordination, and technical configuration all need to come together precisely. This guide provides the frameworks, formulas, and checklists that production managers, video directors, and technical directors use to plan and execute LED video wall productions.

Why Production Planning Matters

LED video wall productions have compressed timelines and zero margin for error. Unlike traditional set pieces, a video wall must be fully operational for content review, camera blocking, and rehearsals. A 16-foot by 9-foot wall using 2.6mm panels requires 90+ individual panels, each needing power, data, and mechanical connection. Multiply that by the crew hours, equipment logistics, and venue constraints, and the complexity becomes clear.

Production Planning for LED Video Walls

The systematic process of coordinating equipment, crew, venue logistics, power distribution, and technical configuration to successfully load-in, operate, and strike LED video wall systems within production timelines.

Poor planning manifests in familiar ways: crew standing idle waiting for equipment, power issues discovered during installation, panels arriving without compatible cables, or testing cut short because setup ran long. These problems are preventable with proper advance work.

Planning Prevents Common Issues

Without Planning

Discover power shortfall mid-install, wait 2 hours for venue electrician

With Planning

Power requirements confirmed in advance, distro staged at load-in

Without Planning

Eight crew members, 200-panel wall, 6-hour load-in window fails

With Planning

Crew sized to timeline, 16 installers plus specialists, completed with buffer

Production Timeline Phases

LED video wall productions follow a predictable timeline from initial inquiry through strike. Understanding these phases helps allocate resources appropriately and identify dependencies.

Phase 1: Pre-Production (4-8 weeks out)

Initial specs, equipment selection, site survey, crew booking, power coordination with venue, permit acquisition if needed.

Phase 2: Prep (1-2 weeks out)

Equipment pull, cable staging, content loading, processor configuration, crew confirmation, trucking logistics, final timeline distribution.

Phase 3: Load-In (show day minus 1-2)

Trucking, unload, rigging, physical installation, power distribution, cabling, processor setup, initial testing.

Phase 4: Tech and Rehearsal

Content review, camera integration, genlock verification, lighting coordination, full show run-through, final adjustments.

Phase 5: Show Day Operations

Pre-show system check, monitoring during show, real-time troubleshooting, operator standby, post-show backup of settings.

Pro Tip: Major productions often run a separate "video rehearsal" day before full tech to work through content timing and processor cues without the pressure of full production rehearsals.

Site Surveys: The Foundation of Every Production

A thorough site survey prevents most production day surprises. This is not a quick walkthrough - it is a systematic documentation of every factor that affects LED video wall installation and operation. Plan for 1-2 hours minimum, and bring measuring tools, camera, and a checklist.

Site Survey

A pre-production venue visit to document physical dimensions, structural capacity, power availability, access routes, and environmental conditions that affect LED video wall installation and operation. Typically conducted 2-4 weeks before production.

Critical Site Survey Checkpoints

Physical Space

  • Room dimensions (width, depth, height)
  • Wall position and viewing distance
  • Floor type and load capacity
  • Ceiling height and obstruction clearance
  • Stage dimensions if applicable

Power Infrastructure

  • Available amperage and voltage
  • Distance from panels to power source
  • Panel box vs. cam-lock availability
  • Backup generator access
  • Who provides tie-in (venue vs. production)

Access & Logistics

  • Loading dock dimensions and height
  • Door clearances to install location
  • Elevator capacity if multi-floor
  • Parking for truck during load-in
  • Staging area for cases and equipment

Rigging Points

  • Existing rigging points (location, capacity)
  • Ceiling structure (steel, concrete, timber)
  • Point load limits per rigging point
  • House rigger availability requirements
  • Ground support option if no fly points

Viewing Distance Check

Optimal Viewing Distance = Pixel Pitch (mm) × 8 to 10

Example: 2.6mm panels → 2.6 × 8 = 20.8 feet minimum viewing distance. If audience is closer, consider smaller pixel pitch.

Never assume rigging point capacity. Always request structural documentation from the venue and have a qualified rigger verify loads per OSHA rigging standards. A single 500mm panel weighs 15-25 lbs - a 100-panel wall plus hardware can exceed 3,000 lbs total.

Crew Sizing & Role Allocation

Undersized crews are the most common cause of blown timelines. LED panel installation requires physical labor (lifting, connecting) plus technical expertise (cabling, troubleshooting). Use these formulas as starting points, then adjust for specific conditions.

Base Crew Sizing Formula

Install Crew = Panel Count ÷ 12 (round up)

100 panels ÷ 12 = 8.3 → 9 installers minimum. This assumes experienced crew and no time pressure.

Time-Compressed Crew Adjustment

Adjusted Crew = Base Crew × (Standard Time ÷ Available Time)

If 8-hour job needs to complete in 4 hours: 9 × (8 ÷ 4) = 18 installers

Specialized Roles Beyond Installers

RoleCountResponsibilities
Video Engineer1-2Processor configuration, color calibration, content loading, input management, show operation
Lead Rigger (ETCP)1Rigging plan, point selection, load calculations, motor operation, safety oversight
Rigger Assistants1-3Hardware assembly, chain management, motor positioning, trim height adjustment
Electrician1Power tie-in, distro setup, load balancing, troubleshooting power issues
Crew Chief1Timeline management, crew coordination, client communication, problem-solving
Pro Tip: Book crew 2-3 weeks in advance for major productions. LED-experienced technicians are in high demand, and last-minute substitutes may slow your install. Confirm certifications: ETCP rigging for lead rigger, licensed electrician for power tie-ins in venues that require it. For union venues, consult IATSE local rules for crew requirements and work hour restrictions.

Load-In Logistics & Timeline

Load-in timelines must account for every phase: trucking, staging, rigging, installation, power, cabling, and testing. Build your timeline backward from show time, adding buffer for each phase.

Load-In

The production phase when equipment is transported to the venue, unloaded, assembled, installed, and made operational. For LED video walls, load-in typically begins 1-2 days before first use to allow adequate testing time.

Phase-by-Phase Time Estimates

PhaseDurationVariables
Truck unload & staging1-2 hoursTruck count, dock access, staging distance
Rigging setup (flown walls)2-4 hoursPoint count, motor installation, truss assembly
Panel installation2-3 min per panelCrew size, wall configuration, accessibility
Power distribution1-2 hoursDistance to power, circuit count, cable runs
Data cabling30-60 minutesWall size, cable organization, redundant paths
Processor setup1-2 hoursConfiguration complexity, input count, genlock setup
Testing & calibration1-2 hoursFull test suite, color correction, content review

Total Load-In Time Estimate

Total Hours = (Panel Count × 2.5 min ÷ Installers ÷ 60) + 6 hours base

100 panels, 10 installers: (100 × 2.5 ÷ 10 ÷ 60) + 6 = 6.4 hours + 6 hours = ~10-12 hours with buffer

Real-World Example: Corporate Conference

24ft × 13.5ft wall using ROE CB5 (500mm panels) = 144 panels

Crew Calculation:

  • • 144 panels ÷ 12 = 12 installers
  • • 1 video engineer + 1 lead rigger
  • • 2 rigger assistants + 1 electrician
  • Total: 17 crew

Time Estimate (12 crew):

  • • Panel install: (144 × 2.5 min) ÷ 12 = 30 min
  • • Rigging + staging: 4 hours
  • • Power/cable/test: 3.5 hours
  • Total: ~8 hours + 20% = 10 hours
Always add 20% buffer to your timeline estimates. Union venues may have mandatory breaks that add 1-2 hours. Equipment issues, missing parts, or venue surprises can derail tight schedules.

Power Distribution Planning

Power planning starts with calculating total draw and works backward to determine circuit requirements. US and EU venues have different standards, and on-location productions may use generators with their own specifications.

Power Distribution for LED Walls

The system of breakers, cables, and connections that delivers electrical power from the source (venue panel, generator) to individual LED panels. Proper distribution ensures balanced loads across phases and adequate capacity for full-brightness operation.

Calculating Power Requirements

Total Power Draw (Watts)

Total Watts = Panel Count × Panel Wattage × Brightness Factor

100 panels × 200W max × 0.5 (50% avg brightness) = 10,000W operating draw

Circuit Count (US 120V / 20A)

Circuits Needed = Total Watts ÷ 1,920W (80% of 2,400W per circuit)

10,000W ÷ 1,920W = 5.2 → 6 circuits minimum

Real-World Example: Power Planning for 144-Panel Wall

ROE CB5 Specifications:

  • • Max power: 230W per panel
  • • Typical (50% brightness): 115W per panel
  • • 144 panels × 115W = 16,560W operating
  • • 144 panels × 230W = 33,120W max

Circuit Requirements (120V):

  • • Operating: 16,560W ÷ 1,920W = 9 circuits
  • • Max (safety): 33,120W ÷ 1,920W = 18 circuits
  • Recommend: 100A 3-phase service
  • • Cam-lok tie-in with 60A distro boxes

Power Planning Checklist

Calculate total wattage at max and operating brightness
Apply 80% derating rule for continuous load
Verify venue capacity with facility manager
Determine cable gauge based on distance (longer = thicker)
Balance loads across phases for 3-phase power
Plan distro location for minimal cable runs
Confirm who provides tie-in (venue vs. your electrician)
Pro Tip: For productions over 50 panels, request cam-lock or powerlock connections from the venue. Standard wall outlets require too many circuits and introduce more potential failure points. Temporary power installations must comply with NEC Article 590 requirements for temporary wiring.

Cable Management Best Practices

Cable management affects both installation efficiency and troubleshooting speed. Consistent, organized cabling reduces setup time and makes it possible to quickly identify and replace problematic connections during a show.

Data Cable Organization

Do

  • Use consistent cable lengths per row
  • Label both ends of every cable
  • Maintain 3-foot service loops at connections
  • Test every cable before installation
  • Create redundant data paths for critical shows

Avoid

  • Running power and data cables together
  • Sharp bends in fiber optic cables
  • Unlabeled connections
  • Cables stretched tight without slack
  • Trip hazards across walkways

Service Loop

Extra cable length coiled near connection points to allow for panel adjustment, easy disconnection, and strain relief. Standard practice is 3 feet (1 meter) of service loop at each end of data cables connecting LED panels.

Pro Tip: Pre-stage cables by length before load-in. Sort and bundle cables by row count so installers can grab the right length without searching through a pile. This alone can save 30-45 minutes on a large install.

Testing Protocols

Testing is not optional - it is when you discover and fix issues before they become problems during the show. A systematic test protocol catches problems that visual inspection misses.

Standard Test Sequence

1

Power-Up Sequence

Progressive load test: power 25% of wall, then 50%, then 100%. Monitor for breaker trips, unusual sounds, or power supply failures.

2

Full White Test

Display solid white at 100% brightness. Check for dead pixels, dim modules, color variation between panels, and visible seams.

3

Primary Color Tests (R/G/B)

Full red, full green, full blue at 50% and 100% brightness. Reveals module-level color issues and LED failures not visible in white.

4

Gradient Test

Display gradients from black to white and through primary colors. Reveals banding issues and bit-depth problems.

5

Motion Test

Play scrolling content or motion test patterns. Look for tearing, frame dropping, or sync issues between panels.

6

Input & Genlock Verification

Connect camera feed, verify genlock sync, check all input sources, test input switching, verify frame rate matching.

7

Show Content Run

Play through actual show content at show lighting levels. Verify timing, transitions, and appearance in production conditions.

8

Backup System Test

If redundant processor or backup playback exists, test failover. Simulate primary failure and verify seamless switchover.

Never skip testing due to time pressure. A 15-minute test protocol can save hours of troubleshooting during the show. If testing reveals issues, document them and communicate to the client before show time.

Show Day Operations

Show day begins hours before doors open. A systematic approach ensures the wall is ready for the audience and crew is prepared to handle any issues that arise.

Pre-Show System Check (2 hours before call)

Power up wall, verify all panels display
Check processor inputs, verify sources
Confirm genlock with camera systems
Test backup processor failover
Verify power readings nominal
Check cable runs for trip hazards
Stage spare panels and modules
Confirm crew has comms and tools

During Show Operations

During the show, video crew should monitor the wall and be ready for immediate response. Position at least one technician with tools and spare parts within 30 seconds of the wall.

Operator Position

At processor with clear view of wall. Manage content cues, input switching, and monitor for issues.

Tech Standby

Backstage with spare panels, modules, and tools. Ready for quick swap during commercial breaks.

Power Monitor

Periodic checks of distro and power readings. First response to any power-related issues.

Pro Tip: Keep a "show bible" document with processor settings, cable routing diagrams, power distribution map, and contact information for all key personnel. This saves time during troubleshooting and enables backup operators to step in if needed.

Common Issues & Solutions

When problems occur, systematic diagnosis is faster than guessing. These are the most common issues and their typical solutions.

Dead/Dark Panel

Single panel not displaying content.

  1. Check power connection to panel
  2. Check data cable connection (both ends)
  3. Swap data cable with known-good cable
  4. Swap receiving card if accessible
  5. Replace panel with spare

Row of Panels Dark

Multiple panels in sequence not displaying.

  1. Check data cable to first panel in chain
  2. Check processor output port
  3. Verify processor configuration includes that output
  4. Check power to row (may share circuit)
  5. Swap sender card or output port if available

Color Shift / Wrong Colors

Panel displaying different color than neighbors.

  1. Check receiving card configuration (may have wrong file)
  2. Re-map panel in processor software
  3. Reload calibration file from backup
  4. Replace receiving card
  5. Replace panel if calibration data is on panel EEPROM

Flickering / Unstable Image

Image flickers or shows intermittent issues.

  1. Check genlock settings and sync source
  2. Verify frame rate match between source and wall
  3. Check for loose data cable connections
  4. Test with different input source
  5. Check power quality (voltage sag from shared circuits)

Production Checklists

Use these checklists to ensure nothing is missed during production planning and execution.

Pre-Production Checklist

Site survey completed with documentation
Equipment list finalized and ordered
Crew booked and confirmed
Power requirements communicated to venue
Rigging plan approved (if flying)
Trucking and dock time scheduled
Timeline distributed to all stakeholders
Content specs sent to content creators

Load-In Kit Checklist

All panels + 5% spare
Data cables sorted by length + 20% spare
Power cables and distro
Processor with content pre-loaded
Spare receiving cards and power supplies
Rigging hardware (if flying)
Tools: multimeter, cable tester, screwdrivers
Cable management: labels, velcro, clips

Frequently Asked Questions

How far in advance should I start planning an LED video wall production?

For major productions, start planning 4-8 weeks in advance. This allows time for site surveys (2 weeks out minimum), equipment availability confirmation, crew booking, power coordination with the venue, and permit acquisition if needed. Smaller corporate events may need only 1-2 weeks, while festival stages require 2-3 months of advance planning due to complex logistics and multiple vendor coordination.

How many crew members do I need to install an LED video wall?

Crew sizing depends on wall dimensions, rigging complexity, and time constraints. A baseline formula: 1 crew member per 10-15 panels for installation, plus dedicated roles (1-2 riggers, 1 video engineer, 1 electrician). A 100-panel wall typically needs 8-12 installers plus specialists. Double crew count if load-in time is cut in half. Factor in 2 crew per motor hoist for flying systems.

What should I check during an LED video wall site survey?

Critical site survey checkpoints: floor load capacity (LED walls range 50-150 lbs per panel), ceiling height and rigging points, power availability (voltage, amperage, distance to distro), truck access and dock dimensions, room dimensions for viewing distance, ambient light conditions, climate control availability, and WiFi/network access for processors. Document everything with photos and measurements.

How do I calculate load-in time for an LED video wall?

Base calculation: 2-3 minutes per panel for physical assembly by experienced crew. Add time for trucking and staging (1-2 hours), rigging setup (2-4 hours for flown systems), power distribution (1-2 hours), cabling (30-60 minutes), processor configuration (1-2 hours), and testing/calibration (1-2 hours). A 100-panel wall typically requires 8-12 hours total with adequate crew. Always add 20% buffer for unforeseen issues.

What cable management best practices should I follow for LED walls?

Key cable management practices: maintain 3-foot service loops at connection points, use consistent data cable lengths per row, label both ends of every cable, separate power and data runs by 12 inches minimum, use cable management accessories (clips, trays, velcro), create redundant data paths for critical shows, test every connection before closing panels, and document cable routing for troubleshooting. Pre-stage cables by length before load-in.

What testing should I do before an LED video wall goes live?

Pre-show testing protocol: 1) Power-up sequence with progressive load testing, 2) Full white test to check for dead pixels and color uniformity, 3) Primary color tests (R/G/B) at 50% and 100% to identify module issues, 4) Motion test with scrolling content for artifacts, 5) Genlock verification with camera feed, 6) Audio sync check with timecode if applicable, 7) Backup processor failover test, 8) Full show content run-through at show lighting levels.

How do I handle power distribution for LED video walls on location?

Power distribution approach: calculate total wattage (average 50W per panel at 50% brightness), apply 80% derating for safety, determine circuit quantity (panels per 20A circuit = 1,920W / panel wattage). Verify venue power capacity, request cam-lock or powerlock connections for large walls, use distro with individual breakers per output, balance loads across phases, and have a generator backup plan. Distance from power source affects cable gauge requirements.

What should be in my LED video wall show day checklist?

Show day essentials: arrive 2 hours before call for system check, verify all panels display correctly, check processor inputs and scalers, confirm genlock with cameras, test backup systems, check cable runs for trip hazards, verify power readings are nominal, have spare panels and modules staged, ensure crew has comms, brief client on emergency procedures, document processor settings, and keep tools accessible for quick fixes.

Ready to Plan Your Production?

Use our calculator to determine panel counts, power requirements, and crew sizing for your next LED video wall production.